Work packages for the construction delivery services at Beacon Barracks for the Defence Estate Optimisation Portfolio. Lendlease are delivering works at Beacon Barracks on behalf of the Defence Infrastructure Organisation involving the reconfiguration and refurbishment of existing infrastructure and construction of new infrastructure to provide the MOD with improved Live/Work/Train requirements.
High-level Scope
The PCC scope of works is primarily for the procurement, fabrication, supply, storage, transport, delivery to site, off-loading, distribution, surveying and setting out, installation, supervision and inspection of all pre-cast concrete (PCC) buildings.
The works shall include all materials, components, fixings, fittings and finishes together with all associated engineering, labour, plant, equipment, supervision, scaffolding (if required)/edge protection, access equipment, and any other elements required to carry out the works in coordination with other Project stakeholders, subcontractors and suppliers.
PCC columns, Core walls, stairs and landings to stair cores, roof slabs.
PCC Lift shaft, allow for cast-in free issue items from lift manufacturer
Additional information:
Minimum Compliance Requirements
Description 1: Lendlease Financial Performance and Accreditation requirements, Lendlease Global Minimum Requirements, Building Information Modelling requirements, BPSS