The London Borough of Barking and Dagenham is pleased to invite you to tender for the construction of an infill extension at John Perry Primary School. The infill extension will form a conference room and quiet area adjacent to the existing library. Internal remodelling to surrounding areas will be required. External works include alterations to fencing and temporary adjustment to play equipment and artificial grass to enable construction works
The works will be at John Perry Primary School, Charles Road, Dagenham, Essex, RM10 8UR
Project Timeline
Tender Return: 17th June 2022
Intended appointment: w/c 27th June 2022
Lead-in Time: 4 weeks
Site set up/Demolition works: Monday 25th July 2022 (Note: 25th July - end August 2021: school summer holiday period)
Completion of works: 16th December 2022 (21-week construction period)
Site visits are strictly by appointment only
Further information and tender documents are available on our e-tendering portal.
Any questions regarding the tender must be addressed through the portal in the messaging section
Additional information:
The Contracting Authority intends to use an eTendering system in this procurement exercise, register and access the full documents at the weblink provided Below