BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The A12 Chelmsford (junction 19) to A120 (junction 25) is part of the strategic road network and supports national and regional economy by connecting Felixstowe and Harwich ports to London. It links the towns of Chelmsford, Witham, Marks Tey and Colchester.
This road struggles to cope with existing peak traffic levels, resulting in delays and reduced speeds. With few available diversions, accidents lead to traffic disruption over a wide area.
The projected growth in population and local development in the area will only increase the pressures on this road.
To ease congestion and cope with increasing traffic, the A12 is to be widened between junction 19 (Chelmsford) and junction 25 (A120 interchange, Marks Tey).
The project is proceeding to Development Consent order and is in PCF stage 3 - Preliminary Design Stage.
Highways England require a snapshot appraisal of the current project estimate with consideration to its cost accuracy, with appraisal of risk provisions and quality of schedule.
Estimator Requirements
A Senior Estimator is required to lead the project cost appraisal works. The scope includes but is not limited to the following:
The estimator shall develop their independent view of the direct works and indirect works costs, informed by but not necessarily based upon pre-existing cost estimate information.
The estimator shall satisfy themselves that the project construction costs and associated Highways England costs are a fair and considered representation of the current position of the design
The estimator shall incorporate risk and schedule information provided by their Risk and Schedule team members and confirm the quality of synergy between the three components.
The estimator will lead liaison with the Risk and Schedule team.
Risk Review Requirements
Working closely with the estimator, the risk appraiser will review the project risk register, Highways England Cost Planning's appraisal or price and quantum range, Project Uncertainty and Portfolio Risk provision. The risk manager shall review the Risk Register with the Project Risk Team with a specific view to it's relationship to the cost estimate and current design the estimate is based upon.
The review shall consider:
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Turner & Townsend | 06468643 | £94,358 | - |
Government spending data: This supplier has received £120,038,428 in 1,736 payments (over £25k) from Department for Transport, Department for Education, Greater London Authority, HMRC, Department for Work and Pensions and 2 more public bodies (2012-06-08 to 2026-05-27). View full payment history →