BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Utilising the Crown Commercial Services (CCS) RM6088 - Construction Works and Associated Services Framework - Lot 10:
Demolition - National Lot across all UK regions.
The Authority required a contractor to undertake the demolition of Crompton Place Shopping Centre (the "Works").
The Works involves the demolition of the existing buildings/structures on the site and associated works to create a clear site which removes the barriers for a future redevelopment scheme, including:
⢠Removal of canopies (to be demolished first within the programme).
⢠Removal of link bridges/structures from the site, and associated making good to the former M&S Building, 33- 35 Victoria Square and 56-58 Bradshawgate.
⢠Retention of the former Bolton Evening News building facade on Mealhouse Lane and associated temporary works.
⢠Grubbing out of the basement slab and foundations to infill the existing car park and provide a level, compacted surface across the site.
⢠Removal of Asbestos Containing Materials.
⢠Erection of a new stairway on the HSBC facade.
⢠Creation of a new pedestrian link from Victoria Square through to Bradshawgate.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Rhodar Industrial Services Limited | 06426331 | £5,098,698 | - |
Government spending data: This supplier has received £6,040,031 in 49 payments (over £25k) from Greater London Authority, Manchester University NHS Foundation Trust, Department for Transport, UK Health Security Agency, Ministry of Justice and 1 more public bodies (2021-03-08 to 2025-09-10). View full payment history →