The Upper Alde & Ore Estuary Embankment Improvements scheme will reduce tidal flood riskand enhance the environment in the Upper Alde and Ore Estuary.
The Alde and Ore Estuary is vulnerable to flooding from the sea made worse by the poor condition of many of the flood defences.
The proposed Flood Cell 06, Snape Maltings scheme is 1 of 4 cells identified to improve the Standard of Service of the existing flood defences and provide resilience to withstand 300mm of overtopping from a 1:200+ year event, given predicted sea levels in 2050.
The Client is theEast Suffolk Water Management Board.
In summary, the scope of Works for the project includes civil engineering works (but is not limited to):
Establish main site offices, compound, temporary services and access routes.
Alliance House - Installation of approximately 20m of new demountable defences along the quay side with piled and concrete slab foundation;
River Alde Quay - Installation of approximately 120m of new demountable defences along the northern quay side with piled and concrete slab foundation;
Henry Moore Lawn - Improvement to approximately 80metres of earth flood embankment to be constructed in a passive fashion to provide improved flood protection and amenity and access value around the Henry Moore Lawn area terminating at the northeastern edge of the Concert Hall building; and
Terrace Car Park - Improvement to approximately 100metres of earth flood embankment, incorporating pedestrian access provision, constructed from the River Cafe terrace area, terminating into the southeast car park area.
The works are estimated to cost around £2.3million.
The form of contract will be a NEC4 ECC Option A.
All tender documents are available through the Client or the Client's appointed tender and contract manager Stantec UK Ltd.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 Sept 2025 – Jun 2026 | £2,300,000 | active |
Changes the buyer published to this notice after it first appeared.
Minor revisions to exisitng tender documents and addition of remaining contract data, scope, site information and activity schedule.
Upload and sharing of FC06 Snape Maltings - Bound CAD Files via two .zip files. Project CAD design files with xRefs bound into the .dwgs.
03/06/2025 updated with TQ, Form of Agreement and Contract Data Part 1&2 revisions.
Upload of 20250606 Technical Amendment No. 2 documentation.
Technical Amendment No. 3_20250619
Also extenstion to tender return deadline, now midday 11/07/2025.