Scope and delivery of the work
The work consists of replacement kitchens and bathrooms. We need a contractor to supply and fit these consistent with the specification attached and in the case of kitchen replacements, liaise with both Housing Solutions and the kitchen supplier to carry out joint design surveys. We currently install Howdens kitchens (Greenwich Range) and will most likely continue to fit these. We do not have a direct relationship with Howdens and expect you to negotiate your own prices with them and allow for the supply in your basket rate. We assume you will engage a Resident Liaison Officer (RLO) and will liaise directly with the residents regarding, surveys, installation dates, general updates, correspondents, access arrangements and any issues that arise before, during and after the works.
Programme scale and duration
We intend appointing for an initial contract period of 3 years with the option to extend for a further two years on a 1 + 1 basis. We operate a two year budget but estimate our 2026-27 - 2028-29 budget will be up to £4m for kitchens and bathrooms and we expect to maintain similar budgets in future years. Therefore we estimate the max term spend to be up to £6.5m.
Geographical distribution
Housing Solutions was originally formed from transferred Local Authority homes in Maidenhead. These still form the majority of our homes, although there are post-1995 developments in Reading, High Wycombe, Slough, Bracknell, Farnborough, Wokingham, and other locations in Berkshire and Buckinghamshire.
Our 2026-27 programme could consist of approximately 300-500 homes across our estate. Around 70% of our stock are within the Maidenhead area, however there are some homes in other areas like Reading, Farnborough, Wokingham, Slough, Windsor, Bracknell.
Programming
We will leave programming of the work to you. We may have a small number of high-priority cases needing to be done earlier, but in general we would give you our address list for each financial year (April to March) and you can determine your own programme to deliver it. We expect that once work on an individual property have commenced, they are completed within 10 working days for kitchens and 8 working days for bathrooms where practicable and these targets will form part of the KPI suite. The priority is to give the tenant clear timescales, which are met. We would expect essential services (kitchen sink, heating, electricity gas and water) to be restored at the end of each working day.
CDM
We will appoint the Quoin Consultancy as Principal Designer, you will be appointed Principal Contractor. We assume you will prepare the key documents and Quoin will check them against the regulations.
Pricing model
Works will be priced on basket rates per the attached specification with variation on M3NHF SOR Version 7.0. There may be an option to put forward an additional / alternative bid that features another brand (not Howdens).
Ordering and payment
Form of contract
The form of contract will be the JCT Minor Works (MW2024)
KPIs
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 Apr 2026 – Mar 2029 | £6,500,000 | planned |
Changes the buyer published to this notice after it first appeared.
We have just noticed that there was an error when the original UK3 Notice was published via our nominated e-tender portal provider last month. It would seem that the 2 documents that had been shared for comment failed to be uploaded - please find them attached now and pass us your thoughts.
Note: Likely timelines for this procurement have been pushed back to accommodate the anticipated market-insights on the draft Service Specification & Pricing Matrix documents shared.
A draft Pricing Matrix and draft Service Specification have been included with this notice for comment - closing date for comments will be 12 noon on 20th June 2025.