Skanska Costain Strabag Joint Venture (SCSJV) are seeking supply chain partners to provide crane maintenance services for the HS2 Main Works Civils Contract Area Central.
The Subcontractor provides all management, people, equipment, plant and materials, consumables (including fuels) and any other resources necessary to carry out and complete the items below.
Timing of work to be agreed 4 weeks prior to planned commencement.
LOLER thorough examination of each crane (e.g., https://www.hse.gov.uk/work-equipment-machinery/thorough-examinations-lifting-equipment.htm).
Periodic LOLER thorough examination according to LOLER requirements Including but not limited to:
ÂWear checks and measurements on brakes, ropes, mechanical and electrical components
ÂVisual inspections and functional checks of all components, including but not limited to brakes and safety devices
ÂAll brakes are visually inspected thus ensuring that the brakes are working efficiently and without undue wear.
ÂVisual checks for defects - all components.
ÂVisual structural inspection of the crane.
ÂNon-destructive testing, load testing and other tests as deemed appropriate by the competent person.
ÂDisassembly or internal examination of parts as required to conduct the above examination items.
ÂAny other checks as specified by the manufacturer.
Report of inspection as per LOLER requirements (e.g. LOLER Schedule 1: https://www.legislation.gov.uk/uksi/1998/2307/schedule/1/made). Immediate notification to Contractor of any defects noted to be a danger to people.
Schedule of examinations to be every 6 months initially (following examination at commissioning) then adjusted as needed according to as per a competent person recommendation taking into account the work environment and historical findings. Adhoc inspections maybe required in the event of exceptional circumstances (e.g. damage).
Bimonthly servicing (every two months). This may be adjusted should the servicing reports indicates more, or less frequent inspections are required.
Upon completion a detailed report to be provided to the Contractor.
Quote for remedial works associated with any defects identified to be provided.
Servicing to consist, as a minimum, of the following:
ÂWear and other defect checks of load ropes
ÂAll safety devices are checked for correct operation and adjusted as required
ÂAll electrical components are checked for wear, cleaned, and adjusted where necessary.
ÂAll brakes are adjusted to the correct settings, thus ensuring that the brakes are working efficiently and without undue wear.
ÂAll safety devices are checked for correct operation and adjusted if required.
ÂAll mechanical components are checked for wear.
ÂFull lubrication program as per OEM and/ or industry recommendations
Subcontractor to provide a breakdown response service which includes out of hours unscheduled onsite work and over the phone assistance. This service to be provided 24x7 unless otherwise agreed.