BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Winterton Town Council are wanting to extend the Winterton Community Pavilion to include in Phase 1 a storage facility for its plant and machinery, and phase 2 is a new build office and club house for the junior football team.
Planning permission and building regs etc have been approved by the local authority North Lincolnshire Council https://apps.northlincs.gov.uk/application/pa-2024-1102 and we now have 3 years to start.
The internal fire door from the main hall will already have been completed.
We would like 2 quotes - phase 1 and phase 2. Funding is already available for phase 1 just need to source funding for phase 2.
Apply to the clerk …@wintertoncouncil.co.uk
No supplier information available.