Demolition Specification
Excavate existing footpath & ground to a depth of 160mm; remove all redundant material from site and dispose. Contractor to agree site measurement with Council representative and document prior to submission.
The Works
Phase 1
Carry out demolition as specified. Lay new footpath; 1.2 meter wide between edgings x 111 meter long to North end of the Tye. Composite edging bedded on and haunched back & front with concrete. Every care must be taken in relation to levels; the contractor must account for water escape from the finished surface and any adjoining hard surfaces.
Phase 2
Carry out demolition as specified. Lay new footpath; 1.2 meter wide between edgings x 119 meter long to South end of the Tye. Composite edging bedded on and haunched back & front with concrete. Every care must be taken in relation to levels; the contractor must account for water escape from the finished surface and any adjoining hard surfaces.
Specification/Notes
Include all site safety barriers for public, maintain public access throughout works. Ensure public Health & Safety during works.
Install weed preventative and weight stabilising membrane to all new works; lay 100mm certified MOT type 1 crushed limestone or equivalent, machine roll.
Adjust all manhole chambers, water/gas stop tap boxes etc in height to new finished surfaced pathway
Lay to total area 40mm 0f 20mm binder course tarmacadam and 20mm 0f 6mm surface course tarmacadam and machine roll.
Tar any joints with hot poured bitumen to seal where new surface meets surrounding surface.
Clear away and make good on completion
Note:
Please provide a price for each Phase as a separate works package including all associated set up costs.
In the event that both Phase 1 & 2 are carried out concurrently please provide your discount for the combined works on the collection sheet