The design, manufacture, supply, installation and commissioning of -
SGS Phase 5 Control Panel Replacement 2026/27
3 No. MCC dual pump Control Panels and 3 No. Single pump control panels including associated works. Partial decommissioning of MCC on one redundant borehole site.
(At the Client's sole discretion, SGS Phase 1 Control Panel
Replacement 2027/28 and SGS Phase 2 Control Panel Replacement
2028/29 below may be instructed via Compensation Event)
SGS Phase 1 Control Panel Replacement 2027/28
2 No. MCC dual pump Control Panels and 5 No. Single pump control panels including associated works. Partial decommissioning of MCC on one redundant borehole site.
SGS Phase 2 Control Panel Replacement 2028/29
1 No. MCC dual pump Control Panels and 8 No. Single pump control panels including associated works.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| ECS Engineering Services Ltd | - | £732,289 | - |